Concrete work estimate template: the lines a slab, a driveway or a footing estimate carries before the truck is ordered

A concrete work estimate template is the contractor's document, not the homeowner's: it turns the takeoff of a slab, a driveway, a footing or a wall into the lines a customer signs and the numbers the company keeps. The material line is the yards with waste, the forms, the rebar or mesh, the vapor barrier and the sealer at the supplier's price; the labor line is the crew's hours for forming, placing, finishing and stripping at a loaded rate; equipment is the pump, the saw and the trowel; then the overhead the job must recover and the markup that leaves a profit. The template on this site prints those lines for one job at a time.

What the customer's copy shows

The customer's estimate shows the scope in plain words, the square footage and thickness, the finish, the reinforcement, the joint layout, what is excluded such as excavation, grading, permits or removal of the old slab, the total, the deposit and the date the price holds until. It does not show the yards, the hours or the markup; those are the company's and stay with the estimate behind the customer's copy.

What the company's copy keeps

The takeoff quantities and the unit prices, the waste allowance, the hours by task and the loaded rate, the pump and equipment, the overhead percentage and the markup, and the notes from the site visit: access for the truck, the subgrade condition, the weather window. When the job closes, the yards ordered and the hours worked are written against the estimate and the next slab is priced from a better number.

Concrete moves with the plant's price

Ready-mix prices change with the plant's schedule and the season, so a concrete estimate carries a date the price holds until and is repriced from the takeoff if the customer signs late. Pro keeps every estimate against the customer and the job with the unit prices it went out at, so repricing is a change to one line rather than a fresh estimate.

Questions people ask about concrete work estimate template

What should a concrete estimate include for the customer?

Scope, area and thickness, finish, reinforcement, joints, exclusions, total, deposit and the price validity date; the yards, hours and markup stay with the company's copy.

How do I estimate the finish hours?

From the crew's own rate per square foot for that finish, broom, trowel or stamped, on similar pours, recorded when jobs close and applied to the next takeoff.

Is the pump an equipment line or a subcontract?

Whichever way the company buys it: a pump the company hires with an operator is a subcontract at the quoted price; the company's own pump is equipment charged per hour or per pour.